Jensen Pipeline

This project is a closed PVC pipeline that replaces the existing lateral canal of the Secondary 'B' Canal system. This starts at Range Road 225 and continues east and ends at Range Road 221 of Crowfoot.

 

WID forces were responsible for the installation of approximately 7.8 km of PVC pipeline of varying sizes 100 mm (4 inch) to 500 mm (20 inch).  The project began in the fall of 2016 and will be completed in the spring of 2017.